Calculate the forward pass and backward pass.

Assignment Help Project Management
Reference no: EM131385164

Earned Value Management Journal Guidelines

Assignment: On April 8, one week before the first internal project review is scheduled to take place, Spencer Tracey and Margaret Porter are reviewing the presentation that Spencer intends to make to their vice president.  Spencer is the project manager and Margaret is the contract manager. The project they are working on has the potential to generate 10 billion dollars over the next 7 years but only if the first year of the project is successfully completed on time (December 31) and within budget ($110 million).  

At this point in April, the project is reporting out its status on the first 25% of the work. Spencer feels optimistic about the outcome. He plans to report that the project is on track financially and is still tracking to plan. All tasks for January and February were completed on time; however, a few tasks in March began to slip. These tasks were caught early enough to implement a corrective action to ensure they finished on time. During the 2nd and 3rd weeks of March, overtime was added to bring the past due tasks back in line with the schedule baseline.

Based off this analysis, Spencer believes he will finish the project under budget at about $100 million dollars and on time. Margaret congratulates Spencer on his success so far and asks if she can review the numbers more closely. Spencer agrees and provides her with the following data:

Work Unit

Completion Date

$M Budget

Planned Percent Complete

Actual Percent Complete

$M Actual Costs

A

Jan 31

4

100

100

5

B

Feb 28

6

100

100

8

C

Mar 31

10

100

80

12

D

Jun 30

30

0

0

 

E

Aug 31

26

0

0

 

F

Oct 31

20

0

0

 

G

Nov 30

2

0

0

 

H

Dec 31

2

0

0

 

Margaret decides to add another column, which she calls the earned value (EV) analysis.  

Complete Margaret's EV chart and answer the questions above based on the earned value analysis of the project. Fill in the missing data in the empty spaces.

Work Unit

Completion Date

$M Budget

Planned Percent Complete

Actual Percent Complete

$M Actual Costs

EV

A

Jan 31

4

100

100

5

 

B

Feb 28

6

100

100

8

 

C

Mar 31

10

100

80

12

 

To Date

April 8

 

------

-------

 

 

D

Jun 30

30

0

0

-------

-------

E

Aug 31

26

0

0

-------

-------

F

Oct 31

20

0

0

-------

-------

G

Nov 30

2

0

0

-------

-------

H

Dec 31

2

0

0

-------

-------

Complete the following earned value calculations to determine the overall status of the project and projected outcome:  

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI) 

Schedule Performance Index (SPI)

Estimate at Completion (EAC)

Estimate to Complete (ETC)

Variance at Completion (VAC)   

If you were Margaret, what would be your analysis of Spencer's plan, current status, and probable outcome of the project? Is the project on schedule and on budget?

Network Diagram Journal Activity

Now that you have created the work breakdown structure and received approval to begin scheduling the office move, your manager, Steve Spaniels, would like to review a network diagram and present it to the CEO.

You have worked with your project team to estimate the durations of each of the work packages in the WBS. The following is your current plan:

Work Package

Duration (days)

Predecessors

1) Initial planning

20

 

2) Kick-off meeting

1

 

3) Decide on furniture

25

 

4) Office preparation

20

 

5) Actual move

5

 

6) Build out of new facility

45

 

7) Install of furniture/servers/equipment

10

 

8) Set up utilities

30

 

9) Pack-out existing office

10

 

10) Install new company signs

15

 

11) Closeout activities

5

 

Assignment:

Please review the Network Diagraming. Create a project network diagram by first identifying the task predecessors (above).  Once you have completed the network diagram:

1) Calculate the forward pass and backward pass.

2) Calculate activity slack and project float.

3) Identify critical path.

Attachment:- Assignment.rar

Verified Expert

This paper is about the time management done by the companies where various activities are involved. The activities could be done in different duration. The solution is done in the MS- office ms- excel. It is an important way to reduce the time consumption as well as cost incurred.

Reference no: EM131385164

Questions Cloud

What strategy should they pursue to obtain cooperation : What problems, if any, do you see with the use of the university's brand?- What strategy should they pursue to obtain cooperation from the university?
Explain the control as feed forward concurrent or feedback : Identify which aspect or metric of the goal they're controlling. Explain the reasoning and value behind the control choice. Identify the control as feed forward, concurrent, or feedback.
What other channels of distribution might tomboy tools use : What are the advantages and disadvantages of the in-home method of selling Tomboy Tools?- What other channels of distribution might Tomboy Tools use?
How can good packaging help a product : What is it about Monster's logo that makes it effective?- How can good packaging help a product?- Why is labeling an important part of the packaging for energy drinks like Monster?
Calculate the forward pass and backward pass. : Please review the Network Diagraming. Create a project network diagram by first identifying the task predecessors (above).  Once you have completed the network diagram: Calculate the forward pass and backward pass. Calculate activity slack and proj..
Find out how they view innovation in their market : Interview the owner or owners of a local manufacturing business to find out how they view innovation in their market. Summarize your findings.
Analyze the policy differences of pepsico company : 175-297 word paper in which you identify and analyze the policy differences of pepsico company . Address the treatment of the following:Exempt employees versus nonexempt employees at PepsiCo company.
Compare the decision making process : Compare the decision-making process you used to the four stages of the new product development process. Report your conclusions.
Which type of forecasting method the company should use : Explain the various methods of forecasting to develop an aggregate forecast. Explain which type of forecasting method the company should use and why.

Reviews

len1385164

2/7/2017 5:14:44 AM

Network Diagram- Entry clearly describes the process of the network diagram including the forward/backward pass, slack/float, and critical path with specific relevant examples. Synthesis- Entry shows excellent evidence of synthesis of the module content and exhibits careful consideration of the topic. Voice - Entry is written in a style that is appealing and appropriate for the intended audience and a consistent voice is evident throughout. Writing - Entry is free of errors in organization and grammar.

len1385164

2/7/2017 5:14:26 AM

Earned Value Management - Entry clearly describes the earned value analysis of the project with specific relevant examples. Calculations - Effectively works with numerical data and solves quantitative problems with accurate calculations. Synthesis - Entry shows excellent evidence of synthesis of the module content and exhibits careful consideration of the topic. Writing - Entry is free of errors in organization and grammar.

Write a Review

Project Management Questions & Answers

  Show the levels of quality

Levels of Quality - Compare the effort needed for the six levels of quality of an automobile to a toothbrush OR SOME OTHER SIMPLE ITEM.

  Evaluate the expected rate of return and standard deviation

Evaluate the expected rate of return and standard deviation for each investment and which investment would you prefer

  Discuss the validity of each statement

Discuss the validity of each statement.- If the statement is always true, explain why. If not, give a counterexample.

  Capital concepts as insights into the maintenance

Summarize the author's main thesis. Analyze the arguments he offers in defense of his position. Explain how relevant Brätland's position is for infrastructure projects in your country or region.

  Find the use of complex models of project risk

Evaluate the use of complex models of Project Risk and Procurement Management; systematically and creatively making sound judgements based on the systematic analysis and creative synthesis of ideas.

  Will revenue increase or decrease

If the current price of an order of fries is $1.29, will a 10% price decrease cause revenue to increase or decrease?- will revenue increase or decrease?

  An adaptive project management life cycle mode

Explain the similarities and differences between an adaptive project management life cycle model and an extreme project management life cycle model.

  How the courts check the power of administrative agencies

Describe how the courts check the power of administrative agencies.-  Describe how the executive branch of government checks the power of administrative agencies.

  Was it fair for the vietnamese catfish importers

Was it fair for the Vietnamese catfish importers to step in and capture market share while the market has been expanded due to the significant efforts and investments of the domestic industry.

  Risk management component of successful project management

Risk management is a major component of successful project management.

  Case study - cbn railway company

Do you think that the decision to lease the locomotives was the best decision for CBN - Case study - CBN Railway Company

  Three major approaches to implementing an information system

What is systems implementation?- What are the systems implementation goals?- What are the three major approaches to implementing an Information System?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd