A popular South-West coastal town in Victoria has a resident population of 6000 people during the winter months (April - November). During the summer months (December - March), the town population increases to 9,000 people due to holiday makers. The population growth rate was expected to be 1.5% per year for winter population and 2.5% per year for summer population during the 25 years design period.
(i) Calculate the winter and summer population expected at the end of design period.
(ii) Assuming an average daily water demand of 400 L/(person. day) during winter months and 700 L/(person. day) during summer months, calculate the annual water demand on the water supply at the end of the design period.
A cutting 9 m deep is to be excavated in saturated clay of unit weight 19 kN/m3. The design shear strength parameters are cu = 30 kN/ m2 and fu = 0. A hard stratum underlies the clay at a depth of 11 m below ground level.
For a substance that decays according to first-order kinetics, what is the equivalent PF rate constant that would be used to describe treatment in a series of three CM reactors in terms of flow (Q), the total volume in the system (V),
A vertical curve is formed when a rural highway passes under a bridge joining a -8% grade to the horizontal grade satisfying the requirement for safe speed of 90 Km/hr . Determine the minimum clearance required betewen the highway pavement surface..
Part of a vertical piping system consists of 8 ft of 4 in diameter, connected to 8 ft of 3 in diameter above, and connected to 8 ft of 2 in diameter above that. Water at 60 F flows up the pipe (no downward flow occurs)
calculate the magnitude and direction of the horizontal force exerted on the contraction (not on the water). Assume that there is no loss of energy in the contraction. Use the gamma of water is equal to 1000 kg/m^3
Calculate the pH of a buffer solution prepared by mixing 8.5g KH2PO4 with 43.5g K2HPO4 in 1 liter of water (this is actually the composition of the dilution water used in a BOD test. Follow the same procedures you have been using for previous acid/..
The continuity equation is just the water balance for the slope or any small portion of the slope and can be given as: p - fp = RO where i = rainfall rate, fp = infiltration capacity, and RO = runoff rate, all expressed as a depth per time
during the next month, the amount of water available for a city is lognormally distributed with a mean of 1 million gallons and a c.o.v. of 40%, where as the total demand is expected to follow a lognormal distribution
a conical tube of length 8 m fixed vertically with its smaller end upwards. the velocity head and pressure head at
Using a safety factor of 2.00 and neglecting the pile dead weight, find the length of a 1' diameter circular concrete pile required to take a design load of 50 kips in a soil composed of two layers.
A catchment has an area of 150 ha and a runo/rainfall ratio of 0.40. If due to a 10 cm rainfall over the catchment a stream flow at the catchment outlet lasts for 10 hr, what is the average stream flow in the period
what is the effect of temperature on compressive strength of concrete?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd