We setup a baseline plan. Now some time has pass since the project started, it's time to check on the progress, make any adjustment to our plan, and take necessary measures to keep our project on track. The methods we use to analyze project progress and to detect problems are called EVA - earned value analysis. As a follow-up, Task 4 starts with the baseline file we created.
To reduce the scope of the assignment, we only enter the actuals for the activities under the first summary task (initiating). Assume that tasks 1, 3, 4, 6, 7, 8 were all completed on schedule. But task 5 was finished three days later than scheduled. Do an earned value analysis for the activities under initiating.
Deliverables
Answer the following questions[1]:
1. What are the BCWS, BCWP, ACWP, SV, CV, EAC, BAC, CPI and SPI for task 5? Briefly explain what do those numbers mean?
2. What are the BCWS, BCWP, ACWP, SV, CV, EAC, BAC, CPI and SPI for the summary task (initiating)? Briefly explain what do those numbers mean?
Electronic file: 660_yourgroupname_control.mpp
PPT file: your team is ready to demonstrate how you perform this task using the ppt file.
[1] Note: BCWS (budgeted cost of work scheduled), BCWP (budgeted cost of work performed), ACWP (actual cost of work performed), SV (schedule variance), CV (cost variance), EAC (estimate at completion), BAC (budget at completion; baseline cost), CPI (cost performance index), SPI (schedule performance index). Use the MS Project Help facility to better understand what these metrics mean, how they are computed and how to interpret them.
Management system for a software development project
: Describe 5 factors you would evaluate in trying to identify a database management system for a software development project.
|
Calculate the cost of preventive renewal
: Calculate the cost of preventive renewal and the cost of renewal on failure per roller for each of the 4 renewal strategies listed in Q1 - Which renewal strategy best represents the current approach being applied to the roller maintenance.
|
Do you think initiatives are critical for successful leaders
: Do you think these initiatives are critical for successful leadership? Why or why not? Did the leader hold managers accountable for diversity practices? How or how not?
|
Implementation of the functions
: But what about the class definitions -- the actual implementation of the functions. Where and how can you implement the functions of a class? Examples?
|
Budgeted cost of work performed
: Note: BCWS (budgeted cost of work scheduled), BCWP (budgeted cost of work performed), ACWP (actual cost of work performed), SV (schedule variance), CV (cost variance), EAC (estimate at completion), BAC (budget at completion; baseline cost), CPI (c..
|
Lessor is responsible for all maintenance and insurance
: Sothern Asia Ltd leased cars from a finance company. a noncancellable contract for 4 years term and started on 1st January 2013. The annual rentals are $25,000 and are made on 1 st January each year with the first rental being paid on 1st January 201..
|
How are liberty and freedom different
: According to John Locke, in your own words, what is freedom, what is liberty, how are liberty and freedom related, how are liberty and freedom different?
|
Do you think another great depression is possible
: Discuss the causes of the Great Depression in terms of what you know about the economy today. Do you think another Great Depression is possible?
|
Difference between the rent paid by the new tenant
: Gamison Ltd has leased a warehouse in an industrial section of the twon. The lease is for 5 years and can only be cancelled by Gamison if Gamisons reimburses the landlord for the costs of re-letting the warehouse including any costs of finding a new ..
|