Baseline project budgets are derived from

Assignment Help Operation Management
Reference no: EM131392581

Progress and Performance Measurement and Evaluation

Project Management Ch 13

6th Edition

1:The second step in the project control process for measuring and evaluating project performance is to

A)Review the baseline plan with top management

B)Analyze inputs to control system

C)Compare plan against actual

D)Measure progress and performance

E)Review spending with team members

2:A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A)Baseline

B)Control

C)Variance

D)Tracking

E)Simple

3:A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a

A)Project control chart

B)Gantt chart

C)PERT chart

D)Network diagram

E)Milestone chart

4:The earned value system starts with the time-phased costs that provide the project baseline, which is called the

A)Planned budgeted value of work scheduled

B)Planned budgeted value of work completed

C)Earned value of work scheduled

D)Scheduled value of work scheduled

E)Scheduled value of work completed

5:The cost variance for a project is calculated by

A)EV-AC

B)AC-SV

C)PV-EV

D)CV-EV

E)EV-PV

6:Baseline project budgets are derived from

A)The organization's overall budget

B)Time-phasing the work packages

C)Top management directions

D)The total direct, direct project overhead and G&A overhead costs

E)The earned value system

7:Of the following costs, which are NOT included in baseline?

A)Suppliers

B)Equipment

C)Labor

D)Budget reserves

E)Contractors

8:Which of the following methods will measure the cost efficiency of the work accomplished to date?

A)SV/CV

B)EV/PV

C)EV/AC

D)AC/SV

E)AC/CV

9:A CPI or SPI value less than one indicates that the project is

A)Under cost or behind schedule

B)Over cost or ahead of schedule

C)Under cost or ahead of schedule

D)Over cost or behind schedule

E)On cost or on schedule

10:The value that tells you the planned value of work that has actually been completed is the

A)SV

B)PV

C)EV

D)AC

E)CV

11:The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the

A)PCIC

B)VAC

C)CPI

D)SPI

E)TCPI

12:Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

A)SV

B)TCPI

C)CPI

D)SPI

E)PCIB

13:Sally receives the following information on her project: PV=100, AC=75, EV=100. How well is the project doing in terms of budget?

A)Right on budget

B)25 under budget

C)25 over budget

D)50 under budget

E)50 over budget

14:Jessica just received the following information on her project: PV =200, EV=300, AC=250, BAC=1500, EAC=1208. In terms of cost at completion

A)The project will currently finish under budget

B)The project will currently finish over budget

C)The project will currently finish on budget

D)The project will currently finish behind schedule

E)There is insufficient information to draw conclusions

15:Which of the following is NOT true regarding scope creep?

A)It commonly occurs late in projects

B)It is frequently unnoticed until time delays or cost overruns are observed

C)It wears down team motivation and cohesiveness

D)Project suppliers resent frequent changes

E)Scope changes can represent significant opportunity

Reference no: EM131392581

Questions Cloud

Show how the gauges are wired into a bridge circuit : Show how the gauges are wired into a bridge circuit to provide temperature compensation. If each gauge has the same gauge factor, GF, derive an equation for the bridge off-null voltage as a function of strain.
Role of the federal reserve bank in regulating the economy : Explain how an easing of monetary policy impacts on the economy through its effect on exchange rates. Explain the role of the Federal Reserve Bank in regulating the economy. When a firm engages in predatory pricing, what strategy does it use to drive..
What is the speed and the distance moved : An object falls from rest near the Earth's surface, accelerating downward at 1 g. After 5 s, what is the speed and the distance moved?
Identify legal and ethical requirements of property sales : CPPDSM4008A  Identify Legal and Ethical Requirements of Property Sales to Complete Agency Work. Briefly explain each of the following titles to land (i.e. land tenure ship): Free hold, Lease hold, and Torrens Title
Baseline project budgets are derived from : Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the.A tool used to monitor past project schedule performance, current performan..
Calculate the average shock in gs : Calculate the average shock in gs experienced by a transistor that falls 1.5 m from a tabletop, if it takes 2.7 ms to decelerate to zero when reaching the floor.
Calculate the peak acceleration in gs : An automobile fender vibrates at 16 Hz with a peak-to-peak amplitude of 5 mm. Calculate the peak acceleration in gs.
True about price matching strategies : Which of the following is true about price matching strategies? consumers are often mislead because they believe they are charged the same price as competing firms. if one consumer finds a lower price at Firm A,then Firm B will match its price to Fir..
Find the maximum acceleration that can be measured : Find the relation between acceleration in and output voltage, the maximum acceleration that can be measured, and the natural frequency.

Reviews

Write a Review

 

Operation Management Questions & Answers

  Explain what is meant by the term what-if analysis

Explain what is meant by the term "what-if analysis". Discuss the four ingredients of an effective training program for process safety.

  Analyzes data of hundreds of billions of shopping with cards

Analyzes data of hundreds of billions of shopping with cards to create campaigns directed of a way one to one.

  Cost based charge based per procedure per diagnosis

The US healthcare system has devised a number of methods to track the services provided by physicians and others in the care of individuals needing services. It is important to know and understand how these methods track care and turn that into reven..

  What type of relocation package would you expect to receive

What steps would you need to take if you were offered a job that resulted in you having to relocate to another state? What type of relocation package would you expect to receive?

  Manufacture and distribution of smartphones

Consider smartphones by Apple. What kind of supply chain should Apple use for the manufacture and distribution of smartphones? Explain your rationale

  Intensity of rivalry tend to increase when

Intensity of rivalry tend to increase when

  What is the risk of a stockout during lead time

A service station uses 1,200 cases of oil a year. Ordering cost is $40, and annual carrying cost is $3 per case. The station owner has specified an annual service level of 99 percent. What is the risk of a stockout during lead time? What level of saf..

  Advantages-risks of using cloud storage for corporate data

Increasingly IT services are being sourced from outside the organisation using them. Explain the advantages and disadvantages of outsourcing an organisations IT. Discuss the advantages and risks of using cloud storage for corporate data.

  Different facility layouts used to manufacture product

Name three different facility layouts used to manufacture product. Give an example that is applicable for each. Does a products’ characteristics dictate the manufacturing process used to manufacture that product or does manufacturing process define t..

  Case study analysis and strategy for the company

The Final Assignment, due in Unit 10, is your chance to bring it all together. This Strategic Management Presentation is an in-depth case study analysis and strategy for the company of your choice. Final Assignment Guidelines are also available in..

  Although experienced project managers often disagree

The Project Management Institute (PMI) states that all projects should be formally closed when following the PMBOK® guide, although experienced project managers often disagree. Identify a possible exception using an example and explain why there shou..

  What is your opinion of honda allowed rate

What is your opinion of Honda's allowed rate and the mechanics' performance?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd