Aoa network diagram representing the project

Assignment Help Project Management
Reference no: EM131404020

Consider the activity list in the table below. All duration estimates or estimated times are in days.

  1. Draw an AOA network diagram representing the project. The network should proceed from Node 1 to Node 9. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
  2. Identify all of the paths on the network diagram and note how long they are.
  3. What is the critical path for this project and how long is it?
  4. What is the shortest possible time needed to complete this project?

Reference no: EM131404020

Questions Cloud

Pre-qualified contractor or designer for non-public project : 1. Selection methods for choosing contractors is done by weighted criteria. Why would an owner choose to use a weighted criteria method to select a pre-qualified contractor or designer for a non-public project?
Pre-qualified contractor or designer for non-public project : 1. Selection methods for choosing contractors is done by weighted criteria. Why would an owner choose to use a weighted criteria method to select a pre-qualified contractor or designer for a non-public project?
How using robots will create better paying farm jobs : Explain how using robots will create better paying farm jobs.
Why number of combination be less than number of permutation : When we are considering n objects taken r at a time, with r 1, why will the number of combinations be less than the number of permutations?
Aoa network diagram representing the project : Draw an AOA network diagram representing the project. The network should proceed from Node 1 to Node 9. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Describe elements that enable employees to become empowered : Describe the four elements that enable employees to become empowered. Compare the five groups of needs in Maslow's theory with the three groups of needs in Alderfer's ERG theory.
What is the marginal product of the sixth farm worker : What is the marginal product of the sixth farm worker? If, when the price of asparagus rises to $3 a bunch, the farm hires eight workers, what is the marginal product of the eighth worker?
Time management instead of scope management : Answer the following item with complete sentences and paragraphs. Why do you think the defining activity is a process of time management instead of scope management?
In how many ways can his request be satisfied : If the purchaser of a vanity plate wants his first three positions to be ROY, in how many ways can his request be satisfied?

Reviews

Write a Review

Project Management Questions & Answers

  Project management - the value of progress reports

Show why are progress reports an integral part of project communications and what should they include? How are they different from a final report?

  Show the cost and time methods

Cost and Time Methods - As a project manager, show the cost and time methods you would chose to work with and why you believe these are the best.

  Open source project management tool

Task: 1) Identify an open source project management tool that could be used as an alternative to Microsoft Project. Try provide a critical comparison of the two tools and evaluation of the technique used = 1000 words.

  Evaluate the break-even point

Separate the expenses between fixed and variable cost per unit. Using this information and the sales price per unit of $6, evaluate the break-even point.

  Advantage and a disadvantage of exclusive distribution

Identify an advantage and a disadvantage of exclusive distribution? How do chains differ from independent retail stores? How do specialty stores differ from variety retail stores?

  Project plan and its execution to disrupt the resources

This excerpt explains what factors might intervene between a project plan and its execution to disrupt the resources assigned to the project.

  What is the density of t

The birth and death probabilities are A= 0.15 and 11 = .05 per animal per year. A hunter wishes to visit the island when he can be 95% sure that the herd has doubled in size. How long will he have to wait?

  Find the transition matrix p and the matrices q and r

For the Markov chain of Exercise , find the average number of years a first-year, second-year and third-year. - Find the transition matrix P and the matrices Q and R.

  Latest current yield and promised yield

Determine the latest current yield and promised yield for each. (for the promised yield use annual compounding). In addition, find the duration and modified duration for each bond.

  Module is to select an organization for your project you

module is to select an organization for your project. you may consider any of these organizations as long as you have

  Question related to expediting a project

Project Manager in the middle of a project and find that one of your project resources is unavailable, what can you do to keep your project one course?

  Describes the nature of the two projects

Submit a Project Proposal that describes the nature of the two projects you will be analysing, your sources of information for these projects and the major concepts, topics, and techniques you plan to address.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd