Annual manufacturing cost-annual savings from purchasing

Assignment Help Operation Management
Reference no: EM131149752

Brian Wilson, materials manager at B&L Inc. in Lancaster, Pennsylvania, was considering a proposal from his purchasing agent to outsource manufacturing for an outrigger bracket. It was the end of April and Mr. Wilson had to evaluate the proposal and make a decision regarding whether to proceed. B&L Inc. Manufactured trailers for highway transport trucks. The company comprised three divisions: the Trailer, Sandblast & Paint, and Metal Fabricating Divisions. Each division operated as a separate profit center, but manufacturing operations between each were highly integrated.

The Metal Fabricating Division produced most of the component parts of the trailers, the Trailer Division performed the assembly operations, and the Sandblast & Paint Division was responsible for completing the sandblasting and final painting operation. B&L manufactured approximately 40 trailers per year, with about two-thirds produced during the period from November to April. The outrigger bracket, part number T-178, was an accessory that could be used to secure oversized containers. The bracket consisted of four component parts welded together, and each trailer sold by B&L had 20 brackets per 10 per side. The Metal Fabricating Division was presently manufacturing the outrigger bracket. The subassembly parts are T-67, T-75, T-69, and T-77 were processed on a burn table, which cut the raw material to size. Although the burn table could work with eight stations, this machine had only been operating with one station. The final assembly operation, T-70, was performed at a manual welding station. Manufacturing lead time for the outrigger bracket was two weeks.

However, the Metal Fabricating Division had been able to coordinate supply and production with assembly operations. Consequently, finished inventory levels of the outrigger bracket were kept to a minimum. B&L's inventory holding costs were 20 percent per annum. In an effort to reduce costs, the purchasing agent, Alison Beals, who reported to Brian Wilson, solicited quotes from three local companies to supply the outrigger bracket. Mayes Steel Fabricators (Mayes), a current supplier to B&L for other components, offered the lowest bid, with a cost of $108.20, FOB B&L. Brian met with the controller, Mike Carr, who provided a breakdown of the manufacturing costs for the outrigger bracket. Looking at the spreadsheet, Mike commented: "These are based on estimates of our costs from this year budget. Looking at the material, labor, and overhead costs, I would estimate that the fixed costs for this part are in the area of about 20 percent. Keep in mind that it costs us about $75 to place an order with our vendors." Numbers below provides B&L's internal cost breakdown and details from the quote from Mayes.

Parts                       Mayes Steel Fabricators                     B&L Manufacturing Costs

T-67                                      $14.60                                               $17.92

T-75                                     $21.10                                               $17.92

T-69                                       $18.50                                               $45.20

T-77                                       $13.00                                               $10.37

T-70                                     $41.00                                                 $58.69

Total                                      $108.20                                              $150.10

Brian expected that B&L would have to arrange for extra storage space if he decided to outsource the outrigger bracket to Mayes, who had quoted delivery lead time of four weeks. Because Mayes was local and had a good track record, Brian didn"t expect the need to carry mush safety stock, but the order quantity issue still needed to be resolved. B&L was operating in a competitive environment and Brian had been asked by the division general manger to look for opportunities to reduce costs. As he sat down to review the information, Brian knew that he should make a decision quickly if it was possible to cut costs by outsourcing the outrigger bracket.

Question:

What is your recommendation for purchasing based on the Annual Manufacturing Cost and the annual savings from purchasing?

Calculations already known are as follows:

Annual Manufacturing Cost: $144,096

Outsourcing Cost: $86,560

Savings by Outsourcing: $57,536

Reference no: EM131149752

Questions Cloud

Share stress reduction technique not yet shared : Share a stress reduction technique not yet shared by a classmate that you use or have seen used. Does it work? Why or why not?
Design a circuit and arduino program that accomplishes : Design a circuit and Arduino program that accomplishes the following. Reads a press of a pushbutton once, and it cycles through all possible brightness values.
Marketing report and company assignment : Discuss its IT architecture - Describe its databases, data warehouse, and data mining.
Drive global air travel growth : Explain the 4 categories of factors that drive global air travel growth. Choose a world region and discuss the most important factors that are expected to affect growth in that region over the next 20 years.
Annual manufacturing cost-annual savings from purchasing : Brian Wilson, materials manager at B&L Inc. in Lancaster, Pennsylvania, was considering a proposal from his purchasing agent to outsource manufacturing for an outrigger bracket. It was the end of April and Mr. Wilson had to evaluate the proposal and ..
How does forbes differentiate itself from competitors : How does Forbes differentiate itself from competitors in the similar market segment(s)? Compare segmentation and targeting strategies of these two companies
Identify the natural frequency and the damping ratio : Suggest a method of using the Bode plot of phase angle versus frequency (Fig. 3.11(b)) to identify the natural frequency and the damping ratio of the system.
What techniques used classify the writer as a postmodernist : Read at least three additional texts by this writer, other than the text required for class. Prove how/why your chosen writer is a postmodernist and how his/her works reflect Postmodern ideology. What topics/subjects presented and what techniques ..
Effects of climate change on the residential building : Analysing the Effects of Climate Change on the Residential Building Cooling Requirements in Manchester, England

Reviews

Write a Review

Operation Management Questions & Answers

  For a machine design capacity is 50 cords per day

for a machine design capacity is 50 cords per day effective capacity is 40 cords per day and actual output is

  Measuring the success of your projects appropriately

You have been criticized that you are not measuring the success of your projects appropriately. Which of the following is not correct about project success?

  Esimate the gas -phase composition

A gas containing Nitrogen, benzene, and tolune is in equilibrium with a 40 mole% benzene 60 % toluene liquid mixture at 100degree centgrade and 10 atm. Esimate the gas -phase composition (mole fraction) using Raoult's law?

  Explain the effective management of an organization

In a four- to five-page paper (excluding title page and references page), select one of the management theories in the textbook. Next, explain the elements that are the foundation of the management theory you selected and how the theory identifies..

  Corporation natural and societal environments

Discuss how a development in a corporation’s natural and societal environments can affect the corporation through its task environment. How can value chain analysis help identify a company’s strengths and weaknesses? What are the advantages and disad..

  The company to be consistent and reach organizational goals

This type of manager ignores the corporate mission, vision and company culture that guides the company to be consistent and reach organizational goals. What resources are available and how would you handle this situation

  Find out the value of the policy variable

Twelve containers are authorized for the part. Recall which p-bar is the average processing time per container not per individual part. Find out the value of the policy variable, α, which expresses the amount of implied safety stock in the system.

  Stated policy on corporate social responsibility

In this project, your teams are consulting companies advising corporations on the substance and public perception of their corporate social responsibility efforts. Does the company have a stated policy on corporate social responsibility?What is the c..

  What were some of the challenges that rim faced to protect

What were some of the challenges that RIM faced to protect its intellectual property, and how did RIM handle those challenges

  Equipment replacement problem

Assume Farmer Dale needs to rent a BEFCO for the four month planting season from Buck & Knobby Equipment Rental. A BEFCO can be rented based on a one-month, two-month, three-month or four months plans. Formulate the LP model to minimize rental costs ..

  1 define price and discuss the two roles price plays in the

1. define price and discuss the two roles price plays in the evaluation of product alternatives.2. list the three

  Monitor quality performance of their wire wrapping operation

A computer manufacturer has decided to initiate a control chart program to monitor the quality performance of their wire wrapping operation on their circuit boards. The boards are randomly tested and those that fail are sent back for rework.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd