McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:

Activity 1: Measure office room dimensions
Activity 2: Estimate cost
Activity 3: Material requisition
Activity 4: Workforce requisition
Activity 5: Special tool requisition
Activity 6: Installation
Activity 7: Inspection and customer acceptance

Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

Activities

OT

MT

PT

Activity 1

4

6

14

Activity 2

5

12

16

Activity 3

7

15

23

Activity 4

13

16

28

Activity 5

17

20

35

Activity 6

20

32

50

Activity 7

5

6

13

You must also do the following:

Determine the expected completion time and the variance for each activity.

Determine the total project completion time and the critical path for the project.

Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity.

What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?

Define project management and the necessary requirements.

Analyze implications of changes in project scheduling.

Evaluate application of project management techniques in terms of the firm's business operational goals and requirements.

Please submit your assignment in an APA-formatted paper.

Submitting your assignment in APA format means, at a minimum, you will need the following:

Title page: Remember the running head. The title should be in all capitals.

Abstract: A summary of your paper, not an introduction. Begin writing in third-person voice.

Body: The body of your paper begins on the page following the title page and abstract page and must be double-spaced (be careful not to triple- or quadruple-space between paragraphs). The type face should be 12-pt. Times Roman or 12-pt. Courier in regular black type. Do not use color, bold type, or italics except as required for APA-level headings and references. The deliverable length of the body of your paper for this assignment is 2-3 pages. In-body academic citations to support your decisions and analysis are required. A variety of academic sources is encouraged.

Reference page: References that align with your in-body academic sources are listed on the final page of your paper. The references must be in APA format using appropriate spacing, hang indention, italics, and upper- and lowercase usage as appropriate for the type of resource used. Remember, the Reference Page is not a bibliography but a further listing of the abbreviated in-body citations used in the paper. Every referenced item must have a corresponding in-body citation.

Objectives:

Assess the general functions of management as depicted by planning, organizing, leading, and controlling.

Reference no: EM131172723

Questions Cloud

Describe how the economic theories deepened your thinking : Briefly summarize and describe how the economic theories and principles you have studied in this course have deepened your thinking about economic behavior.
The determinants of productivity consider simple economy : The determinants of productivity Consider a simple economy whose only industry is fishing. In this industry, productivity—the amount of goods and services a worker can produce per hour—is measured by the number of fish one fisherman catches per hour.
Compute the volume flow rate through the meter : Compute the volume flow rate through the meter that will cause the mercury to flow into the throat. Note that for a given manometer deflection h, the left side will move down h/ 2 and the right side would rise h/2.
Compute the total cost of the potential job : Compute the total cost of the potential job using machine hours to assign overhead. Assume that the bid price is based on full manufacturing cost plus 25% mark up. What is Tom's bid price?
Analyze implications of changes in project scheduling : Determine the expected completion time and the variance for each activity, Determine the total project completion time and the critical path for the project and Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activi..
Two products-safe cars and dangerous cars : Theres two products: "safe cars" and "dangerous cars"
Llc for breach of fiduciary duty : Discuss whether Acme is liable to Zappa and the other members of the LLC for breach of fiduciary duty.
How individual economic decisions affect the market failure : Explain how individual economic decisions affect this market failure and how economic principles can be applied to modify those individual decisions to help correct the market failure.
Conscientious delaware directors : Briefly explain why reasonably conscientious Delaware directors should not be too concerned about liability for violation of the monitoring duty established in Caremark.

Reviews

Write a Review

 

Marketing Management Questions & Answers

  Deceptive marketing practices

What deceptive marketing practices have you personally witnessed

  Finding new innovative ideas to increase brand recognition

Brand awareness in marketplace in the 14th year will maintain above 70%, while also finding new innovative ideas to increase brand recognition

  How information in the article can inform marketing strategy

Explain how the information in the article can inform marketing strategy. That is, how is the information presented important to a marketer in designing a marketing strategy

  How should marketers deal with language differences

What are the differences between a global consumer culture positioning, foreign consumer culture positioning, and local consumer culture positioning? What types of products are more and less environmentally sensitive?

  Best development process of a new product

With the help of taking one product in mind what are the steps you will apply in the best development process of a new product?

  Create a strategic plan and present the plan

Your group will create a strategic plan and present the plan in a professional manner. The plan requires a paper turn in to the Assignment Folder and a PowerPoint presentation that is presented in the last week of class

  How has power been constructed in china

What does a "civilization state" mean? How can it use various "systems" to run the "whole?" and What is the relationship of the Chinese society and the State?

  Appraise the individual and organizational consequences of

1.compare and contrast the mis in place in two distinctly different organizations.2.compare each organizations use of

  Prepare a presentation of international marketing plan

You will soon be presenting your international marketing plan to the board of directors of EduTot using a professional PowerPoint presentation. Devote the time needed to properly review, revise, and edit your work.

  The power of reality shows

The Power of Reality Shows

  Marketing plan for frito lay canada

Marketing Plan for Frito Lay Canada

  Marketing plan format

Marketing plan format is one that is utilized by major corporations all over the country. However, writing a comprehensive marketing plan is a difficult and challenging task, yet, the ability to write such a plan is critical to the development of a m..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd